The First Fix Plumbing works consisted of water supply pipework and waste water plumbing.
Part A (1st Month)
Others: Hacking Works
Digging hole to relocate the main drain (waste water downstairs) Main drain (downstairs): 5 pipes drain waste water from the toilet, dry kitchen and wet kitchen
Part B (2nd Month)
Others: Concrete Works
Cement mix to cover up the drain during concrete works
Part C (4th Month)
Others: Skylight installation (first half), Electrical First Fix, Purchasing Tiles
Installing pipework for Dry Kitchen Water Supply and Waste Water Drainage Installing pipework for Wet Kitchen Water Supply and Waste Water Drainage Pipeworks for Waste Water Drainage
Part D (5th Month)
Other: Hacking & Plastering, Tiling
Direct Water Supply and Waste Water Pipeworks in Wet Kitchen (Before Plastering) Waste Water Pipeworks in Wet Kitchen (After Plastering) 2 Inlet & 1 Outlet in Wet Kitchen Inlet Pipe in Backyard